SUPPLYING AND INSTALLING ICE TANK SYSTEM

SUPPLYING AND INSTALLING ICE TANK SYSTEM

Location: Thang Long I Industrial Zone, Ha Noi City

Starting date: 04/2021

Hand-over date: 06/2021

Project’s information:

  1. Concrete tank (mm): 8500x3000x6000
  2. Cold holdover capacity: 5600 Kw
  3. Installing chiller and renovating cooling mode 7°C – 12°C to cooling mode (−4)°C – 12°C
  4. Improving pipes, making ice to store energy during off-peak hours, defrosting during peak hours.
  5. Building tanks; renovating chiller, pipes in tight spaces, complex foundations, many water supply and drainage projects, and electrical systems.

SUPPLYING AND INSTALLING ICE TANK SYSTEM

Place: Dong Anh District, Ha Noi City

Categories:

Tags: dự án mới, M&E project,